124-128 Brixton Hill Update

Works are progressing well on our project on Brixton hill. After a few hard months in the ground, decontaminating the site which former use was a petrol station, combined with a high water table provided its challenges. The first floor slab has been poured to program and we are now steaming towards a complete frame in February 2017. A big thanks to all involved.